Clubhouse Renovations, Page 10 - Updated 3/25/07


With the exception of the kitchen and patio, we're down the the "little" stuff.

  • Final Coats of paint are going on.
  • The Bag Room has been rebuilt with individual compartments for each bag.
  • The Pro Shop is finished with Nick working hard at stocking it with lots of new stuff.
  • The restaurant seating area is done with just some finishing work needed.
  • The Ladies' Locker room is done, complete with live plants
  • There's all new flooring and carpeting throughout the whole clubhouse
  • The new public restrooms just need the stall partitions installed. The Ladies Room gets a live plant!
  • The Snack Bar is 99% done
  • The Grill Room is done

The new kitchen is almost complete with lots of new appliances being installed.

March 23rd
New Appliances waiting to be installed
Kitchen Walls are covered in stainless
Grill Room is ready to serve the regulars.
Patio Prep work starts again now that the snow is gone.